FREQUENTLY ASKED QUESTIONS

Project Overview

St. Louis MetroLink Green Line (formerly the Northside-Southside Jefferson Avenue Alignment) is a transformational transit project that will connect residents to growing job centers in Downtown West and Midtown, educational opportunities, and healthcare services making St. Louis a more equitable and thriving city for all people. The Project Goals include providing more choices and access to growing and established job centers for residents with limited transportation options, and to invest in historically underserved or marginalized neighborhoods. 

  • Although Palm St./Salisbury St. Station, Russell Avenue Station, and Arsenal St. Station were removed and are now design options, stations continue to be located every mile or less with narrower platforms, sidewalks and buffer allowances and decreased lane capacity. This translates into fewer property impacts and lower costs.
  • Removal of the Palm St./Salisbury St. Station helps avoid potential building and business impacts. Residents in this area will be served by the Grand Blvd./Fairground Park Station or St. Louis Ave. Station. The St. Louis Ave. Station also has greater bike and pedestrian access as well as connections to the upcoming Brickline Greenway.
  • Removal of the Russell Ave. Station avoids property and/or pedestrian impacts on businesses and a learning academy. Alternatively, the Park Ave. Station provides greater neighborhood access.

The project will have parking lanes as well as drive-through lanes. In some places, the project team is evaluating accommodating bicycle lanes. There would still be two lanes of traffic in certain segments. In other segments, potentially in the southern segment, it might go down to one lane in order to retain parking along the way.

There would still be two lanes of traffic in certain segments. In other segments, potentially in the southern segment, it might go down to one lane in order to retain parking along the corridor.

The Project Team has done preliminary studies on the suitability of the bridge to accommodate light rail. Preliminary analysis has shown the bridge can handle the addition of light rail. Further studies, by the project team, will determine the required modifications, configuration, and operations and will be integrating the findings into the design of the guideway crossing the bridge. The project team is also communicating with the Missouri Department of Transportation (MoDOT) to use the I-64 bridge crossing and designing the bridge to carry the light rail. The project team will be conducting a traffic analysis to understand how the proposed light rail would affect traffic on the bridge and throughout the corridor.

The project team is looking at the balance between more stations and overall cost. Currently, with the proposed stations, the Green Line has about a 19-minute end-to-end travel time. The distance between each station is less than a mile. The station design options are being considered in the environmental analysis. BSD is investigating the impacts on neighborhoods – as well as the impacts on ridership. BSD will evaluate travel times, headways, and different walksheds and conduct a traffic study to assess the pedestrian – walking distance, and vehicle driving distance between the stations. (A walkshed is the area around the station – or any central destination – that is reachable on foot by the average person.) The project team’s goal is to have a project that meets the requirements to obtain federal funding under the competitive Capital Investment Grant (CIG) program. For more information on the CIG program, see https://www.transit.dot.gov/CIG.

The trains will be running on a 10 minute – headway/frequency and a transfer station will be located near the I-64/Jefferson Interchange with elevator access to MetroLink’s Red and Blue lines below the Jefferson bridge.

The project, once funded by local funds and federal grants, would start construction in 2027/2028 on utility relocations, followed by street and station buildout. The target date for revenue service, opening day, would be late 2030-early 2031.

An important part of the preparation necessary to build the Green Line is the relocation of utility lines and equipment before building new infrastructure. Advancing this utility relocation ahead of major construction activities allows for a more efficient and streamlined construction effort. The work will include relocating water lines, sewer lines, communications lines, and where applicable overhead power lines.

The decision to choose light rail over electric buses often involves a trade-off between long-term benefits (e.g., capacity, permanence) and upfront costs. While light rail vehicles are more expensive initially, they historically provide higher capacity and attract more riders. City residents also voted in 2017 for a tax increase to support light rail expansion on the north-south corridor.

Environmental Study

The St. Louis MetroLink Green Line has advanced to the environmental review and 30% design phase. NEPA (National Environmental Policy Act) requires that state or local governments seeking federal funds for a project conduct an environmental review. This review ensures the project does not significantly impact key environmental resources (i.e. air quality, water, natural habitats) or low-income individuals or communities of color. Other possible impacts to consider during environmental review are parking, access, noise and parks. The NEPA process will take approximately 12 months.

During 30% design, project costs, timeline and major design elements such as the stations, lighting and pedestrian sidewalks will be fine-tuned. The project team continues to work diligently to identify cost savings. 

Project Partners

BSD is responsible for leading the project planning, design and construction. Once the Green Line is built, Metro Transit, a BSD enterprise, will operate and maintain the alignment.

Noise/Construction

No, the current design does not include an underground option.

The project is currently in the environmental review process and preliminary design. The process will take about a year. The environmental determination document will be submitted to the Federal Transit Administration (FTA) for their review.

  • Once the FTA determines that the environmental analysis complies with laws under the National Environmental Policy Act, the project will be able to advance some early construction activities like utilities.
  • Once the project is rated and completes the necessary requirements it will advance into FTA’s Engineering phase which includes final design and will put the project in line for Federal Full Funding Grant Agreement.
  • Once approved for a Federal grant, the project will go out to bid.
  • BSD will review the bids and select a contractor (s) to construct the project.
  • Property acquisition and utility relocation work will be first and could occur as early as 2026.
  • The main construction work is anticipated to begin in 2027, as long as the Federal grant money is available. If the grant money is delayed, the project may be delayed.

Other

Accessibility Toolbar